PROJECT OVERVIEW
This project consisted of renovating the controllers department in the 3rd and 4th floors of the CSC building. All finishes were replaced and the conference rooms were demolished and rebuilt to accommodate the new layouts, IT requirements and new furniture. This project was completed in multiple phases as the building was occupied with staff and visitors. Great care was taken to avoid dust migration to the surrounding areas as well
as coordinating with the staff to schedule noisy activities at times that caused the least disruption.
​
​
Current Phase: Project Complete
Construction Services Provided: General Contractor Low Bid
Owner: FIU Facilities Management
Owner Contact: Eduardo Arteaga
Email: arteagaj@fiu.edu
Phone:305-348-4613
Architect/Engineer: Via Design Studio