PROJECT OVERVIEW
The project scope includes the removal of approximately 13,000 SFof procelain tile, installation of temporary flooring and installation of finalterrazzo flooring. Also included in the scope is replacing the existinghandrail system in the second floor. Given the continuous school traffic,the project has been executed in multiple phases to ensure the large-scaletile installation proceeds with minimal disruptions to the students’ and staff’sclasses and events.
Current Phase: In Construction
Completion Date: Estimated 08/2024
Construction Services Provided: CM Negotiated Contract
Owner: Miami Dade College
Owner Contact: Luis Rodriguez
Email: lrodri39@mdc.edu
Phone: 786-603-0167
Architect/Engineer: Via Design Studio