Medical Campus flooring replacement

Miami Dade College

About 20,000 square feet of worn-out flooring replaced with terrazzo, one section at a time, in a building students and staff use every day.

CLIENT

Miami Dade College

DELIVERY

CM at Risk (GMP)

SCOPE

≈20,000 SF demolition and terrazzo

ARCHITECT

Harvard Jolly Architecture

STATUS

Completed

THE PROJECT

New floors for a campus that never closes.

Miami Dade College brought D.Torr in as Construction Manager at Risk to replace the Medical Campus's original flooring. The scope covered demolition of roughly 20,000 square feet of deteriorated tile and installation of new terrazzo through the building's main corridors and common areas.

The work ran in two phases. Demolition was timed to Summer Break, and terrazzo went in by section so classes, events and foot traffic could keep moving around it.

HOW IT WAS DELIVERED

01

Demolition in Summer Break

The loudest work happened while classes were out.

02

Mock-ups approved first

Color and finish were signed off before any terrazzo was poured.

03

Installed in controlled sections

Clean, safe paths stayed open for students and staff.

04

Every step logged in Procore

Dated photos, inspections and pay applications, shared in real time.

Before: Medical Campus flooring replacement

BEFORE

After: Medical Campus flooring replacement

AFTER

THE CHALLENGE

An old floor, an open building and a tight calendar.

The building stayed open most of the year, so work had to fit inside school breaks. The existing flooring was very old and badly deteriorated, and demolition uncovered conditions no drawing showed, the kind of surprise that can stall trades and blow up a schedule.

Campus access and event schedules also shifted week to week, so the installation plan had to move with them.

our approach

Plan around the calendar. Inspect before you pour.

Construction step 1: Medical Campus flooring replacement

01

Plan with facilities early

We met the college's facilities team and trades well ahead of each break, so crews and materials were ready when the window opened.

Construction step 2: Medical Campus flooring replacement

02

Surface hidden conditions fast

Substrates were inspected after demolition. Unexpected conditions went straight to the owner so they could be resolved quickly.

Construction step 3: Medical Campus flooring replacement

03

Install in controlled sections

Continuous checks for flatness, joint alignment and finish, with clean, safe pathways kept open beside every active area.

Construction step 4: Medical Campus flooring replacement

04

Resequence every week

The schedule was updated weekly and re-sequenced in real time around events, so progress never stopped and milestones held.

from the field

Construction Sequence

RELATED PROJECTS

More projects like this.

AHC3 Room 316 renovation

Florida International University (FIU)

AHC3 Room 316 renovation

Operable partition retrofit with electrical, lighting, mechanical, drywall and ceiling upgrades.

Read More

Education

GC 265 and 267 suite remodel

Florida International University (FIU)

GC 265 and 267 suite remodel

Suite remodel with a phased main entry door, delivered on budget.

Read More

Education

West Campus flooring and handrail

Miami Dade College

West Campus flooring and handrail

13,000 sq ft of tile replaced with terrazzo, new handrails, phased.

Read More

Education

North Campus EMS labs

Miami Dade College

North Campus EMS labs

Five classrooms converted into five EMS laboratories, a storage room and a control room.

Read More