CLIENT
Miami Dade College
DELIVERY
CM at Risk (GMP)
SCOPE
13,000 sq ft of tile replaced with terrazzo, new handrails.
ARCHITECT
Via Design Studio
STATUS
Completed
THE PROJECT
A new floor under constant foot traffic.
At Miami Dade College's West Campus, D.Torr removed about 13,000 square feet of porcelain tile, installed temporary flooring, finished the space in terrazzo and replaced the second-floor handrail system.
HOW IT WAS DELIVERED
01
Open the whole way through
Safe pedestrian paths stayed open in every phase.
02
No trip hazards
Demolished areas were inspected before temporary flooring went down.
03
Terrazzo with the college seal
New terrazzo throughout, with an inlaid college seal in the lobby.
04
Every handrail inspected
Anchoring, height and code compliance checked on every run.

BEFORE

AFTER

THE CHALLENGE
Demolition, flooring and rails in the busiest spaces on campus.
Students and staff walked through the work area every day, and demolition, temporary flooring, terrazzo and handrail work all had to happen in the same busy spaces.
our approach
Phase it, protect the path, check it twice.

01
Break it into phases
The work was split into clearly defined phases, so each area could close, be finished and reopen while the rest of the building stayed in use.

02
Vet the submittals
Terrazzo and handrail submittals were checked for durability and code compliance before anything was ordered.

03
Inspect before temporary floors
Every demolished area was inspected before temporary flooring went down, so transitions stayed smooth and hazard-free.

04
Work around campus life
Work hours and areas shifted around daily activities and events, and the schedule was updated weekly with the college's representatives.
from the field
Construction Sequence