West Campus flooring and handrail

Miami Dade College

About 13,000 square feet of worn porcelain tile replaced with terrazzo, and a new second-floor handrail, in a building students crossed every day.

CLIENT

Miami Dade College

DELIVERY

CM at Risk (GMP)

SCOPE

13,000 sq ft of tile replaced with terrazzo, new handrails.

ARCHITECT

Via Design Studio

STATUS

Completed

THE PROJECT

A new floor under constant foot traffic.

At Miami Dade College's West Campus, D.Torr removed about 13,000 square feet of porcelain tile, installed temporary flooring, finished the space in terrazzo and replaced the second-floor handrail system.

HOW IT WAS DELIVERED

01

Open the whole way through

Safe pedestrian paths stayed open in every phase.

02

No trip hazards

Demolished areas were inspected before temporary flooring went down.

03

Terrazzo with the college seal

New terrazzo throughout, with an inlaid college seal in the lobby.

04

Every handrail inspected

Anchoring, height and code compliance checked on every run.

Before: West Campus flooring and handrail

BEFORE

After: West Campus flooring and handrail

AFTER

THE CHALLENGE

Demolition, flooring and rails in the busiest spaces on campus.

Students and staff walked through the work area every day, and demolition, temporary flooring, terrazzo and handrail work all had to happen in the same busy spaces.

our approach

Phase it, protect the path, check it twice.

Construction step 1: West Campus flooring and handrail

01

Break it into phases

The work was split into clearly defined phases, so each area could close, be finished and reopen while the rest of the building stayed in use.

Construction step 2: West Campus flooring and handrail

02

Vet the submittals

Terrazzo and handrail submittals were checked for durability and code compliance before anything was ordered.

Construction step 3: West Campus flooring and handrail

03

Inspect before temporary floors

Every demolished area was inspected before temporary flooring went down, so transitions stayed smooth and hazard-free.

Construction step 4: West Campus flooring and handrail

04

Work around campus life

Work hours and areas shifted around daily activities and events, and the schedule was updated weekly with the college's representatives.

from the field

Construction Sequence

RELATED PROJECTS

More projects like this.

AHC3 Room 316 renovation

Florida International University (FIU)

AHC3 Room 316 renovation

Operable partition retrofit with electrical, lighting, mechanical, drywall and ceiling upgrades.

Read More

Education

Medical Campus flooring replacement

Miami Dade College

Medical Campus flooring replacement

About 20,000 sq ft of flooring replaced with terrazzo, phased around the summer break and classes.

Read More

Education

GC 265 and 267 suite remodel

Florida International University (FIU)

GC 265 and 267 suite remodel

Suite remodel with a phased main entry door, delivered on budget.

Read More

Education

West Campus parking garage repairs

Miami Dade College

West Campus parking garage repairs

Parking structure restoration with new sealants, joint systems, traffic coatings and expansion joints.